Archive for the ‘Runway Repaving Project’ Category

Runway Rehabilitation Completed

Monday, May 18th, 2009

MONDAY, May 18th

The rehabilitation of the runway at Williamson-Sodus Airport began on Monday, May 18th and was completed on Friday, June 22nd.   The entire runway was been milled, and new blacktop was  put down.    The taxiway work includes the six short connecting taxiways between the runway and the long taxiway.

Milling & Cleanup

Milling & Cleanup

May 18, 2008 - Runway Surface Milled

May 18, 2008 - Runway Surface Milled

Milling & Cleanup

Milling & Cleanup

Milling & Cleanup

Milling & Cleanup

By late afternoon, the repaving had started.

Paving begins

Paving begins

New Blacktop Surfacing starts late Monday afternoon

New Blacktop Surfacing starts late Monday afternoon

Monday afternoon paving continues

Monday afternoon paving continues

TUESDAY, May 19th

Paving continues at a good pace on Tuesday, with the new surface starting with the crown at the centerline.  By noon, the first 15′ wide row was finished.  By 2:30 pm, the second 15′ row of asphalt was well underway.

101_3023web

New asphalt goes down on Tuesday afternoon.

101_3032web

101_3018web

John Moretto (ADO) from the New York office of the FAA gets a tour of the airport on Tuesday.

One of several asphalt trucks delivering fresh asphalt from a local manufacturer.

One of several asphalt trucks delivering fresh asphalt from a local manufacturer.

By late afternoon, our contractor had finished the middle of the runway, leaving only one more pass on the north and south before they begin work on the short connecting runway exits.

From approach end of Runway 10.

From approach end of Runway 10.

Wednesday, May 20th

Connecting taxiway to runway 10-28 ready for blacktop.

Connecting taxiway to runway 10-28 ready for blacktop.

Paving continues.

Paving continues.

Paving continues.

Paving continues.

By late afternoon on Wednesday, the new surface was just about complete on the runway.  Temporary markings should be painted on Friday, with permanent markings painted a couple weeks later.

View from the south side of the runway looking northeast toward the open hangars.

View from the south side of the runway looking northeast toward the open hangars.

A view from the air by the only means available…from a helicopter looking northwest.  A special thank you to BAC Services for the photo.

Nearly completed runway surface.  View is from the southeast.  (Courtesy BAC Services)

Nearly completed runway surface. View is from the southeast. (Courtesy BAC Services)

Thursday, May 21st

Paving is complete, right on schedule.  Painting of temporary markings will be done on Friday.

The paving is complete!

The paving is complete!

Friday, May 22

Painting

Temporary markings have been painted on the runway

Temporary markings have been painted on the runway

The crews worked on Friday to paint temporary markings on the runway.  In a few weeks, they’ll return and paint permanent markings.

Fresh hold lines at the west end of the runway.

Fresh hold lines at the west end of the runway.

Lance Merritt and Dave Knight walk the entire length of the new surface inspecting for debris prior to opening the runway.

Lance Merritt and Dave Knight walk the entire length of the new surface inspecting for debris prior to opening the runway.

Now that the runway is open, fly!

This public posting of project status was a requirement of the American Recovery and Reinvestment Act.

KSDC Receives Grant to Repave & Repaint Runway 10-28

Tuesday, March 17th, 2009
10-28

Runway 10-28 (in the background) awaits resurfacing.

New York Senators Charles Schumer and Kirsten Gillibrand have announced that the Williamson-Sodus Airport has been awarded a Grant to repave our runway.   The funds come from an Economic Recovery Project Grant to rehabilitate and repave runway 10-28.  The total amount of the grant will be $438,600.00

The project has already been sent out to bid and the winning bid was submitted by Babcock Enterprises, Ltd of Dansville, NY.

The project calls for the runway to have 1″ milled off the top, and 2″ of new asphalt put back down.  The project will take about a week to do, which will require that the runway be closed.  Construction will begin on or around May 18th and will take a week to ten days.

During this time, the runway will be closed.

For more information about the American Recovery and Reinvestment Act, please follow this link.